|
|
-
This Table provides the fees for the survey of land for agriculture purpose including land for aquaculture purpose or survey for subdivision, amalgamation and partition in rural areas.
-
The survey fees chargeable under this Table for each job shall consist of the following charges: .
2.1 AGRICULTURE PURPOSE
-
basic charge per job - RM 1,000.00.
-
charge for the preparation of pre-computation plan shall be RM20.00 per lot, subject to a minimum charge of RM350.00 per job.
-
charge for survey for the re-establishment of old boundary marks found missing or out of position is RM170.00 for each mark refixed or replaced.
-
charge for survey of land for the purpose of new alienation or partitioning where the alienated lot or the original lot to be partitioned is 5 hectares or less are as follows:
| |
Size of Lot |
Charge per lot (RM) |
(i) |
Lot of less than 0.5 hectare |
400.00 |
(ii) |
Lot of 0.5 hectare but less than 2.5 hectares |
800.00 |
(iii) |
Lot of 2.5 hectares but less than 5 hectares |
1,200.00 |
-
Charge for survey of each agriculture lot other than (d) above -
| |
Size of Lot |
Charge per lot (RM) |
(i) |
Lot of less than 0.5 hectare |
740.00 |
(ii) |
Lot of 0.5 hectare but less than 2.5 hectares |
1,660.00 |
(iii) |
Lot of 2.5 hectares but less than 5.0 hectares |
2,350.00 |
(iv) |
Lot of 5.0 hectares but less than 10.0 hectares |
3,320.00 |
(v) |
Lot of 10.0 hectares but less than 15.0 hectares |
4,060.00 |
(vi) |
Lot of 15.0 hectares but less than 20.0 hectares |
4,690.00 |
(vii) |
Lot of 20.0 hectares but less than 25.0 hectares |
5,250.00 |
(viii) |
Lot of 25.0 hectares but less than 30.0 hectares |
5,750.00 |
(ix) |
Lot of 30.0 hectares but less than 35.0 hectares |
6,210.00 |
(x) |
Lot of 35.0 hectares but less than 40.0 hectares |
6,640.00 |
(xi) |
Lot of 40.0 hectares but less than 45.0 hectares |
7,040.00 |
(xii) |
Lot of 45.0 hectares but less than 50.0 hectares |
7,420.00 |
(xiii) |
For each additional 1 hectare or part thereof above the first 50 hectares |
100.00 |
-
Charge for survey of lines for azimuth, connections, controls and minimum survey is RM2.00 per metre
-
Where the survey data is required to be submitted in digital format, an additional charge of 20% of the charges under paragraphs (b), (c), (d) and (e) above is applicable.
-
In security areas -
-
here security pass or permit has to be obtained from the relevant authority, an additional charge of 25% of the charge under paragraphs (a), (c), (d) and (e) is applicable; or
-
here armed escort is required and working hours are dictated by the relevant authority, an additional charge of 50% of the charges under paragraphs (a), (c), (d) and (e) above is applicable; and
-
here there is a waiting time after mobilisation, an additional charge at RM 870.00 per party day shall be applicable.
-
The above charges are applicable when the survey worksite is within 1 kilometre from the nearest motorable road. For distances beyond the first 1 kilometre, additional charges are to be applied as follows:
| Distances to worksite from motorable road |
Rate |
0 kilometre to 1 kilometre |
no additional charge |
Above 1 kilometre but not more than 5 kilometres
|
add 20% to the charges under paragraphs (a), (c), (d), and (e) |
Above 5 kilometres but not more than 10 kilometres
|
add 40% to the charges under paragraphs (a), (c), (d) and (e) |
Above 10 kilometres
|
add 70% to the charges under paragraphs (a), (c), (d) and (e) |
.
-
Professional consultation and meeting fees, reimbursements and charge for supply of transparencies and additional prints, where applicable, are as provided under Table XII, Table XIII and Table XIV respectively.
2.2 AQUACULTURE AND OTHER SIMILAR PURPOSES
-
Basic charge per job - RM 1,000.00.
-
Charge for the preparation of pre-computation plan shall be RM20.00 per lot, subject to a minimum charge of RM350.00 per job.
-
Charge for traversing including connections for azimuth, connections and controls, is RM8.00 per meter
-
Charge for survey for the re-establishment of old boundary marks found missing or out of position is RM170.00 for each mark refixed or replaced.
-
Where the survey data is required to be submitted in digital format, an additional charge of 20% of the charges under paragraphs (b), (c) and (d) above is applicable.
-
In security areas -
-
where security pass or permit has to be obtained from the relevant authority, an additional charge of 25% of the charge under paragraphs (a), (c) and (d) above is applicable; or
-
where armed escort is required and working hours are dictated by the relevant authority, an additional charge of 50% of the charges under paragraphs (a), (c) and (d) is applicable; and
-
where there is a waiting time after mobilisation, an additional charge at RM 870.00 per party day shall be applicable.
-
The above charges are applicable when the survey worksite is within 1 kilometre from the nearest motorable road. For distances beyond the first 1 kilometre, additional charges are to be applied as follows:
| Distances to worksite from motorable road |
Rate |
| 0 kilometre to 1 kilometre |
no additional charge |
| Above 1 kilometre but not more than 5 kilometres |
add 20% to the charges under paragraphs (a), (c) and (d) |
| Above 5 kilometres but not more than 10 kilometres
|
add 40% to the charges under paragraphs (a), (c) and (d) |
| Above 10 kilometres |
add 70% to the charges under paragraphs (a), (c) and (d) |
Professional consultation and meeting fees, reimbursements and charge for supply of transparencies and additional prints, where applicable, are as provided under Table XII, Table XIII and Table XIV respectively.
|